New tasks have estimated durations

Specifies that all new tasks have estimated durations.

If you enable this setting, all new tasks will require estimated durations.

If you disable or do not configure this setting, the user's default setting is used.

Supported on: At least Windows 7
Registry Pathsoftware\policies\microsoft\office\15.0\ms project\options\scheduling
Value Namenew tasks have estimated durations
Enabled Value1
Disabled Value0